Crypt conversion, St Mary’s Islington, London
As project architect for Matthew Lloyd Architects LLP
- Context: Grade II Listed 18th century church
- Involvement: from Production Information to Completion
- Role: specification writing, detailing, liaison with client, local authorities, consultants, suppliers and contractors, site inspections, defects monitoring.
- Construction period: January 2009 to June 2009.
- Contract: JCT, Intermediate Form.
- Construction cost: £ 228,000.
As project architect for Matthew Lloyd Architects LLP
- Context: Grade II Listed 18th century church
- Involvement: from Production Information to Completion
- Role: specification writing, detailing, liaison with client, local authorities, consultants, suppliers and contractors, site inspections, defects monitoring.
- Construction period: January 2009 to June 2009.
- Contract: JCT, Intermediate Form.
- Construction cost: £ 228,000.